European PPA prices rose 5% in September as contracting recovered
Pexapark's EURO Composite index rose with forward power and gas prices, led by Great Britain; 25 PPAs for 1.2 GW were disclosed, and flexible power agreements doubled to 2.1 GW.
Contributing writer
Writes about energy policy and the distance between what a decision says and what it does to a bill.
Pexapark's EURO Composite index rose with forward power and gas prices, led by Great Britain; 25 PPAs for 1.2 GW were disclosed, and flexible power agreements doubled to 2.1 GW.
The Energy Storage Contract Alliance, whose 22 members include Neoen, BW ESS and MN8, released a buyer-side BESS supply agreement covering traceability, inspection, cybersecurity and payment terms.
The Rosatom-built unit achieved a sustained chain reaction on 11 October, three days after regulatory approval; power start-up is scheduled for 20 November.
The GRIP award totals about $581m with cost-share and is expected to add roughly 2.5 GW of grid capacity; together with a SPARK reconductoring project, TVA's planned investment nears $741m.
CRE has authorised anticipated, shared works that create 2,500 MW of connection capacity in the Fos-Lavéra industrial zone by 2029, with part available earlier; connecting industrial users pay a set share of the cost.
A request for qualification opens the first phase of Eskom Green: Eskom brings at least 2 GW of solar and 1 GW/4 GWh of batteries on its own sites, and a five-year panel of co-development and co-investment partners will bid for projects.
The CRE benchmark for household gas offers goes to 194.90 euros per MWh including tax from 1 November, up from 182.88. Bills indexed to it rise by about 12 euros in November; fixed-price contracts are unaffected.
The closure report for delivery increments 24 and 25 of the Open Balancing Platform shows both missed the 80% predictability target; storage parameters under GC0166 and the PEF forecast link went live, and the P1-ready platform goal slipped a month.
CRE has proposed the parameters for the first long-term auction of France's new capacity mechanism: a target of 82 GW, of which 3 GW may get multi-year contracts, and caps kept at 72 and 15 euros per kW.
Rosatom says the VVER-1200's primary circuit held 24.5 MPa, about one and a half times operating pressure; hot tests with all four main pumps at 260°C or more must follow before fuel can be loaded.