Grid operators file large load interconnection reforms at FERC
Most major US grid operators have now filed their proposals at the Federal Energy Regulatory Commission for connecting data centres and other large loads, Utility Dive reported on 17 November. FERC issued "show cause" orders in June, saying operators appeared to lack adequate rules for adding large loads, and listed five issues: application and study processes, prevention of cost shifts and transparency, co-location and behind-the-meter generation, new services for flexible large loads, and studies for generation serving nearby loads. The filings came on Monday, ISO New England's on Friday; the Southwest Power Pool is due to file by Friday.
The centrepiece of PJM's plan is a Fast Energization Process that would study large load and generation requests together in a single one-year process, which PJM says is about twice as fast as today. PJM also filed a separate proposal requiring large computational loads to ride through grid disturbances, and its transmission owners filed their own tariffs on rates, cost allocation and financial protections.
CAISO plans new service options for flexible large loads that can cut their use when transmission capability is unavailable. MISO proposed a Large Load Project Review process and pro forma cost recovery agreements meant to prevent cost shifting, plus a Grid Responsive Integration Transmission Service. NYISO proposed Firm and Non-Firm Withdrawal Services and a State Exempt Load Project exception on resource adequacy. ISO-NE proposed publishing the network upgrades and cost estimates identified for each large load, and requiring large loads to bring their own new capacity.

Why it matters
Every filing answers the same two points from FERC's list in its own way: who pays for the upgrades, and whether a large load can connect sooner by agreeing to be curtailed. PJM's is the one that changes the study itself, putting loads and generators into one queue.