X-energy hires Fluor for nuclear island work at its second Xe-100 project, Cascade
Fluor already works on the Seadrift project in Texas; Cascade plans four 80 MWe reactors with room for twelve.
Fluor already works on the Seadrift project in Texas; Cascade plans four 80 MWe reactors with room for twelve.
The CNNC plant in Jiangsu pairs two Hualong One units with a high-temperature reactor to supply a petrochemical park.
CGN completed initial fuel loading on 2 November using semi-automatic equipment; the unit is scheduled to supply power in 2027.
The New Mexico plant is licensed to enrich up to 10% U-235 in all its cascades; LEU+ allows longer reactor cycles and can feed HALEU production.
The pour began on 31 October at the Shandong site, about 6,626 cubic metres over nearly 62 hours, for the fifth of six large pressurised water reactors planned there.
The study, partly funded by the US State Department's FIRST programme, follows ČEZ's exit from the project company JESS; Slovakia targets completion of the new unit by 2040.
Unit 1 has been off since 28 July and unit 2 since 12 August; a local rise of about 10 cm in the intake basin is not yet enough, and the level must hold and rise for several days.
Talks over a lump-sum subcontract failed; a new contractor is to be chosen by July 2027, while the reactor and turbine supply contracts with Doosan Enerbility stay in force.
Rosatom flew the TVEL-made assemblies in and trucked them to site storage; unit 1 reached criticality on 11 October and its first refuelling fuel is already on site.
The 1,025 MWe Westinghouse units near Busan, offline since their 40-year licences lapsed, may now run until 2034 and 2035 after a four-year safety review.