NuclearThe regulator finished its review of TVA's application in 14 months, four ahead of schedule. TVA has not set a construction date and is still negotiating cost sharing with industry partners.
NuclearAt the UK Fusion Forum, the government's new director for nuclear and fusion said the challenge is no longer proving the science but building supply chains, skills and regulation, with the STEP plant at West Burton as the vehicle.
NuclearSPIC began pouring about 6,637 cubic metres for the unit's nuclear island on 27 September, nine months after unit 1. The two-unit first phase is budgeted at about CNY40 billion and planned for 56 months.
NuclearThe Hualong One unit on Hainan started up in July and joined the grid on 1 August. Its twin unit 4 is due in early 2027, when Phase II should supply 18 TWh a year.
NuclearOne previously used assembly tipped over inside the vessel. Holtec says it was not reportable under NRC rules, is building retrieval equipment and will need a licence amendment to remove it.
NuclearA white paper on denial and delay of radioactive material transport names six causes, from perception to insurance, and was presented at the IAEA General Conference ahead of the group's final meeting in December.
NuclearPreussenElektra demolished one of the last landmarks of Germany's first plant decommissioned under the phase-out. The containment is due to go this year and regulatory release in autumn 2027.
NuclearPEJ and the consortium aim to finish negotiating the construction contract for Poland's first nuclear plant by year-end, with first power still targeted for 2036.
NuclearTX-1 in Oak Ridge is built and moves to equipment installation. At 700,000 pebbles a year it would fuel up to eleven Xe-100 reactors - one of which has a customer and a site.
NuclearUSTDA will pay for technical assistance to TUNAS covering the policy, institutional and financial roadmap Turkish private firms would need, plus a review of how US designs fit.