Linea Energy finances its 500 MWh Mesa View battery in Texas
NORD/LB led debt financing and DESRI committed preferred equity for the 250 MW/500 MWh Mesa View BESS in Upton County, due online in 2027.
NORD/LB led debt financing and DESRI committed preferred equity for the 250 MW/500 MWh Mesa View BESS in Upton County, due online in 2027.
Alongside the existing Eraring battery, the site would reach about 1,200 MW and 8,600 MWh. The new project would have its own connection to Transgrid's network.
The Pedroso and Valkyria deals bring the batteries covered by the two companies' hybrid PPAs in Spain to 1,022 MWh. Three of the four projects are existing solar plants that the contracts make it worth adding storage to.
The PSC conditionally selected the 400 MW Chalk Point and 40 MW Jade Meadow III projects for 15-year, 4-hour awards under the Next Generation Energy Act, at an estimated 7 cents a month per household.
Linxon, Hitachi Energy and FTC Solar sign an EPC framework; Samsung commits $1bn to KKR's Helix; TerraFlow pairs flow batteries with solid-state transformers at a live compute site.
The Independent Planning Commission cleared 804 MW of wind and a two-hour battery near Hay, under a ruling with no court appeal. Transmission access covers only about 262 MW so far.
About PLN500m of loans plus around PLN1bn in state grants back two projects with 17-year capacity contracts, due online in 2028. Polish storage won 11 GW in the capacity market.
Green Energy Corridor Phase III puts INR 500 billion into storage and INR 1.37 trillion into transmission to carry up to 135 GW of renewables by FY2032-33, as curtailment soars.
Draft rules require storage of 50% of connection capacity for two hours, or 25% for four hours, and 1 MWh per MW of connectivity until 2030, rising to 2 MWh after.
Grid access for sites of 1 MW and up would depend on matching each hour, with toll surcharges of up to 500%. A developer argues that makes batteries a licensing condition.