AnalysisBritain will not release the list behind its data-centre figure, PJM's rules are upheld against a developer who missed a deficiency notice, and Spain writes its allocation criteria into a public consultation. Same problem, three levels of openness.
GridA request for project-level data on the roughly 315 data centres in Britain's connection queue was refused as unclear, with advice on how to ask again - and a hint that project detail will stay withheld.
MarketsThe commission found PJM followed its tariff when it dropped the Virginia nuclear, fuel-cell and gas hybrid from the current study cycle, but told the grid operator to work harder with developers.
StoragePower Electronics broke ground in Houston and Heron Power aims at Morgan Hill by late 2027. The same headline capacity from two companies, and neither has published a ramp curve.
GridGSR037 restructures definitions into a table and renumbers Section J. The justification is that a hard-to-navigate standard slows down every other code modification.
MarketsJudge Chutkan found the EPA acted without congressional authority. Rhode Island had already ruled the termination procedurally unlawful. A third suit by 22 states was dismissed in January.
NuclearTX-1 in Oak Ridge is built and moves to equipment installation. At 700,000 pebbles a year it would fuel up to eleven Xe-100 reactors - one of which has a customer and a site.
RenewablesEleven projects, 4.1 GW and 49.9 GWh across two Boralmac rounds for €265 million. Completion is set for 2035, and the cheapest megawatt-hours reuse infrastructure that already exists.
PolicyAdequacy assessments across the EU were being built on fragmented national cost assumptions. ACER published a common CONE dataset on 30 July, and a dashboard with it.
AnalysisSpain's cheapest storage sites are old mines. TRISO-X has a 40-year licence before it has equipment. A court restored $7bn. And Ofgem approved a rewrite justified by drafting speed.